- My Forums
- Tiger Rant
- LSU Recruiting
- SEC Rant
- Saints Talk
- Pelicans Talk
- More Sports Board
- Fantasy Sports
- Golf Board
- Soccer Board
- O-T Lounge
- Tech Board
- Home/Garden Board
- Outdoor Board
- Health/Fitness Board
- Movie/TV Board
- Book Board
- Music Board
- Political Talk
- Money Talk
- Fark Board
- Gaming Board
- Travel Board
- Food/Drink Board
- Ticket Exchange
- TD Help Board
Customize My Forums- View All Forums
- Show Left Links
- Topic Sort Options
- Trending Topics
- Recent Topics
- Active Topics
Started By
Message
re: Boh Bros will finish construction on Napoleon in the year ________
Posted on 3/21/14 at 9:48 am to Hu_Flung_Pu
Posted on 3/21/14 at 9:48 am to Hu_Flung_Pu
That's the one.
Posted on 3/21/14 at 9:51 am to The Sad Banana
That's not Boh Bros though
Posted on 3/21/14 at 9:53 am to Hu_Flung_Pu
It says Napoleon Ave Seg I and IV is near 100%. That's definitely not all of it though.
This post was edited on 3/21/14 at 10:07 am
Posted on 3/21/14 at 9:54 am to alexman
quote:
Boh Bros will finish construction on Napoleon the day after change orders are outlawed
Posted on 3/21/14 at 9:54 am to The Sad Banana
You must have missed i10 construction in baton rouge
Posted on 3/21/14 at 10:02 am to The Sad Banana
quote:
Have you seen the construction on LA 73 from US 61 to I-10? Dear God.
i think my daughter will graduate from college before they finish this
Posted on 3/21/14 at 10:05 am to alexman
When will Jefferson get done? That street is fricked
Posted on 3/21/14 at 10:12 am to alexman
Digging up the road and putting in a new drainage system isn't something you can do quickly. Just wait when New Orleans decides to replace the broken 100 + year old water lines that leak throughout the city.
Posted on 3/21/14 at 10:18 am to Hu_Flung_Pu
quote:
quote:
That entire piece of LA 73 is taking way, WAY too long. It's like nothing is happening.
lol I looked it up. It's a whopping 47% done if it's the widening job.
HU???
Do you work for the state?
This post was edited on 3/21/14 at 10:19 am
Posted on 3/21/14 at 10:47 am to lsuCJ5
quote:
Do you work for the state
si
Posted on 3/21/14 at 11:02 am to Hu_Flung_Pu
Ok Hu, could you answer a question for me? You mentioned Barber Brothers is 47% complete with the HWY 73 project, and I agree that seems about right. I did some research on their contract. When they submitted their bid they had to say how many days they would require to build the job. Barber used 660 days. Their work order was issued on 9/25/2011. If my math is correct they are 907 days into their contract, or 137% on time and 47% complete. How has the state not thrown them off the job for too big of a spread of work complete vs. time? The state sure did it to Austin on I-10????
I have emailed the state numerous times and they keep on blaming it on rain delays and utility conflicts. I realize this has something to do with it, but not everything. The last email I received from the state said they would be complete by this summer. At this rate they will be done 1,929 days or late 2016. Do you have any insight on this? I am ready to battle.
I have emailed the state numerous times and they keep on blaming it on rain delays and utility conflicts. I realize this has something to do with it, but not everything. The last email I received from the state said they would be complete by this summer. At this rate they will be done 1,929 days or late 2016. Do you have any insight on this? I am ready to battle.
Posted on 3/21/14 at 11:13 am to alexman
The project is supposed alter the parade routes for carnival season 2015, so can only imagine how big of a shitshow it will be during Mardi Gras next year. I pretty much take Gen. Pershing or Milan depending on the way I'm going exclusively now.
Posted on 3/21/14 at 11:16 am to alexman
When did it start? Seems like forever that the construction has been there.
Posted on 3/21/14 at 11:17 am to Dav
My bud works for Boh and he said they just ordered a huge culvert for uptown. 4 years, 86 Million dollars.
When will the construction end?
Never.
When will the construction end?
Never.
Posted on 3/21/14 at 11:19 am to Dav
quote:
When did it start? Seems like forever that the construction has been there.
First or second quarter of 2012 I believe
Posted on 3/21/14 at 11:23 am to Rouge
quote:
quote: Boh Bros will finish construction on Napoleon the day after change orders are outlawed
If it weren't for dumb frick engineers there wouldn't be so many change orders ......
Posted on 3/21/14 at 4:27 pm to tigerswin03
quote:that S-class aint gonna pay for itself
If it weren't for dumb frick engineers there wouldn't be so many change orders ....
Posted on 3/21/14 at 4:52 pm to Geauxld Finger
No that was Austin Road and Bridge that fricked it up and got ran off.