re: Boh Bros will finish construction on Napoleon in the year ________

Posted on 3/21/14 at 9:48 am to
Posted by The Sad Banana
The gate is narrow.
Member since Jul 2008
89507 posts
Posted on 3/21/14 at 9:48 am to
That's the one.
Posted by Hu_Flung_Pu
Central, LA
Member since Jan 2013
22542 posts
Posted on 3/21/14 at 9:51 am to
That's not Boh Bros though
Posted by Hu_Flung_Pu
Central, LA
Member since Jan 2013
22542 posts
Posted on 3/21/14 at 9:53 am to
It says Napoleon Ave Seg I and IV is near 100%. That's definitely not all of it though.
This post was edited on 3/21/14 at 10:07 am
Posted by Rouge
Floston Paradise
Member since Oct 2004
138349 posts
Posted on 3/21/14 at 9:54 am to
quote:

Boh Bros will finish construction on Napoleon the day after change orders are outlawed
Posted by Wooly
Member since Feb 2012
13851 posts
Posted on 3/21/14 at 9:54 am to
You must have missed i10 construction in baton rouge
Posted by CurDog
Member since Jan 2007
28153 posts
Posted on 3/21/14 at 10:02 am to
quote:

Have you seen the construction on LA 73 from US 61 to I-10? Dear God.


i think my daughter will graduate from college before they finish this
Posted by tigersownall
Thibodaux
Member since Sep 2011
16840 posts
Posted on 3/21/14 at 10:05 am to
When will Jefferson get done? That street is fricked
Posted by Diddles
LA
Member since Apr 2013
6981 posts
Posted on 3/21/14 at 10:12 am to
Digging up the road and putting in a new drainage system isn't something you can do quickly. Just wait when New Orleans decides to replace the broken 100 + year old water lines that leak throughout the city.
Posted by TigerWise
Front Seat of an Uber
Member since Sep 2010
35131 posts
Posted on 3/21/14 at 10:16 am to
I won't live to see it.
Posted by lsuCJ5
Holly Springs, NC
Member since Nov 2012
1077 posts
Posted on 3/21/14 at 10:18 am to
quote:

quote:


That entire piece of LA 73 is taking way, WAY too long. It's like nothing is happening.




lol I looked it up. It's a whopping 47% done if it's the widening job.


HU???

Do you work for the state?
This post was edited on 3/21/14 at 10:19 am
Posted by Hu_Flung_Pu
Central, LA
Member since Jan 2013
22542 posts
Posted on 3/21/14 at 10:47 am to
quote:

Do you work for the state


si
Posted by lsuCJ5
Holly Springs, NC
Member since Nov 2012
1077 posts
Posted on 3/21/14 at 11:02 am to
Ok Hu, could you answer a question for me? You mentioned Barber Brothers is 47% complete with the HWY 73 project, and I agree that seems about right. I did some research on their contract. When they submitted their bid they had to say how many days they would require to build the job. Barber used 660 days. Their work order was issued on 9/25/2011. If my math is correct they are 907 days into their contract, or 137% on time and 47% complete. How has the state not thrown them off the job for too big of a spread of work complete vs. time? The state sure did it to Austin on I-10????

I have emailed the state numerous times and they keep on blaming it on rain delays and utility conflicts. I realize this has something to do with it, but not everything. The last email I received from the state said they would be complete by this summer. At this rate they will be done 1,929 days or late 2016. Do you have any insight on this? I am ready to battle.
Posted by AlexLSU
Member since Jan 2005
25341 posts
Posted on 3/21/14 at 11:13 am to
The project is supposed alter the parade routes for carnival season 2015, so can only imagine how big of a shitshow it will be during Mardi Gras next year. I pretty much take Gen. Pershing or Milan depending on the way I'm going exclusively now.
Posted by Dav
Dhan
Member since Feb 2010
8149 posts
Posted on 3/21/14 at 11:16 am to
When did it start? Seems like forever that the construction has been there.
Posted by The Levee
Bat Country
Member since Feb 2006
11747 posts
Posted on 3/21/14 at 11:17 am to
My bud works for Boh and he said they just ordered a huge culvert for uptown. 4 years, 86 Million dollars.

When will the construction end?

Never.
Posted by AlexLSU
Member since Jan 2005
25341 posts
Posted on 3/21/14 at 11:19 am to
quote:

When did it start? Seems like forever that the construction has been there.


First or second quarter of 2012 I believe
Posted by tigerswin03
SAINTS / PELICANS FAN
Member since Jan 2009
4715 posts
Posted on 3/21/14 at 11:23 am to
quote:

quote: Boh Bros will finish construction on Napoleon the day after change orders are outlawed


If it weren't for dumb frick engineers there wouldn't be so many change orders ......
Posted by lsuCJ5
Holly Springs, NC
Member since Nov 2012
1077 posts
Posted on 3/21/14 at 4:25 pm to
paging hu flung pu....
Posted by Rouge
Floston Paradise
Member since Oct 2004
138349 posts
Posted on 3/21/14 at 4:27 pm to
quote:

If it weren't for dumb frick engineers there wouldn't be so many change orders ....
that S-class aint gonna pay for itself
Posted by bencoleman
RIP 7/19
Member since Feb 2009
37887 posts
Posted on 3/21/14 at 4:52 pm to
No that was Austin Road and Bridge that fricked it up and got ran off.
first pageprev pagePage 2 of 4Next pagelast page

Back to top
logoFollow TigerDroppings for LSU Football News
Follow us on X, Facebook and Instagram to get the latest updates on LSU Football and Recruiting.

FacebookXInstagram